< Return to Transportation

Divided Highway Signing Improvements - Eastern ND

divided highway signage

Lowry Engineering worked as a consultant on this project through the NDDOT Fargo District in 2014. This project consisted of the removal and replacement of highway signing at intersections along various divided highways in the Devils Lake, Grand Forks, Valley City, and Fargo districts. The intent was to update the signs to the 2009 MUTCD standards as well as replace existing signs to maintain retro reflectivity requirements. Over 18,000 feet of sign post and 13,000 square feet of sheeting was installed. Lowry Engineering monitored the day-to-day activities of the contractor to verify that work was being done in accordance with the plans, and we kept all project documentation such as quantities, pay estimates, and materials certifications.